A12/A14 Traffic Modelling/Ipswich Area Transport Modelling
Date Started: 01/04/2008
Date Ended: 31/03/2009
Growth Point
Development of a fully multi-modal transport model for the greater Ipswich area that will be compliant with department for Transport standards.
Project Scope
Principal Ipswich travel to work area.
Aims
Develop a multi-modal transport modelling tool for appraisal of transport and development options.
Outcomes
A functioning, fully validated transport model.
Dave Watson, Suffolk County Council
01473 631184
HGP Contact: Helen French, Senior Regeneration Manager (Haven Gateway)
Status
Funding for 2008/09 £750,000
Status as at 30 September 2008:
- Survey work undertaken for traffic, road side interviews, bus passenger interviews/counts.
- Drafted model spec report
- Accession baseline report undertaken.
Status as at 31 December 2008:
- Repeat traffic counts undertaken.
- Survey analysis, matrix building and network development all to be progressed.
- Model assembly commenced.
Status as at 31 March 2009:
- Base highway network model development completed.
- Base public transport model development completed with some over-run.
- Highway matrix model has been completed with some delay.
- Highway model calibration started.
- Draft demand model is ready for testing.