North Colchester Local Delivery Framework Release

Date Started: 01/04/2008

Date Ended: 31/03/2010

Growth Point

The adopted Core Strategy for Colchester includes a greenfield allocation for 2200 units to the west of Mile End Road.  Precise site boundaries will be agreed through the Site Allocations Development Plan Document (DPD), scheduled for submission in November 2009. Detailed masterplanning work is required to inform a subsequent Supplementary Planning Document (SPD) for the allocation setting out infrastructure requirements; phasing; land use; circulation; and design guidelines

Project Scope

Initial masterplanning work and evidence gathering will identify the supporting infrastructure requirements for the site along with key environmental and physical constraints.  This work will then be used in the next programme year to inform the preparation of an Area Action Plan. 

The second phase incorporating a draft document for public consultation commences April 2009 and adoption is expected by April 2010.  Public sector funding will be more than matched by private funding and offers best value as it enables specialist consultants to be employed to carry out the work which otherwise could not be afforded and avoids duplication of both CBC and developers carrying out the same work.

Aims of the Project

To produce a Supplementary Planning Document (SPD) to be adopted as part of the Colchester LDF.  This will provide detailed guidance for developers to provide clarity and a consistent approach to assist delivery. 

Outcomes of the Project

To ensure comprehensive sustainable development of a large urban extension that is well supported by infrastructure and successfully integrated with surrounding communities.

 

Local Authority Contact: Karen Syrett, Colchester Borough Council
01206 506477

HGP Contact: Helen Code, Senior Regeneration Manager (Haven Gateway) 
helen.code@essex.gov.uk

 

Status

Funding for 2008/09 £35,000

IDP Package: Colchester North

Status as at 30 September 2008:

  • Consultation work commenced.

Status as at 31 December 2008:

  • Stakeholder and project meetings have taken place.
  • Masterplanning work for the North Colchester greenfield land allocation is being carried out jointly with the developers of the land.

Status as at 31 March 2009:

  • Stage 1 complete.
  • Stage 1 report received.

Status as at 30 June 2009

  • Draft plans/options paper produced.
  • Steering group meeting held.

Status as at 30 September 2009

  • Draft plans/options paper amended.

Status as at 31 December 2009:

  • Draft SPD produced and meeting held with Myland Parish Council representatives.
  • Portfolio Holder Report prepared to authorise public consultation.

 Project complete.